July 2018
Phase 1 Demolition completed July 2nd.
Framing in lobby and gym room commences July 6th.
Tile removal in pool access passageway commences July 9th.
All tile including library corridor has been removed as of July 12th. 
Additional lobby plumbing changes completed July 17th.
Electrical contractor begins their scope of work on Wednesday July 18th.​
Electrical sub-panel installed in exercise room on July 24th.
Recess ceiling framework completed on July 24th.

Future Closet for Chair Storage.
Social Room East Wall, Cabinetry Removed
Pool Passageway Closed July 9
 for Tile Removal.
Passageway Tile Removed
Passageway Tile Removed
Dormant pipe removal above recess lobby ceiling.
Completed metal framework for recess ceiling
New electrical sub-panel in exercise room