August 2018
Floor Tiling to begin August 1st.
Tiling is approximately 2/3 complete on the lobby level as of August 17th.
Inspection passed for lobby area to begin drywall.
Gym and Kitchen inspected and passed according to revised plans.
Drywall installation completed Friday, August 31st. 
​Tiling is 100% complete on lobby level, 95% complete on garage level.
New Tile Leading to Pool Door
Temporary runner in place
New Kitchen electrical for appliances
North Corridor Tiling Complete
Service Entrance Tiling Complete